https://privatebin.net/?16acdd07966dca9d#E8Q5fEz4f4KKAoL2uoxFLaWd7sPc8PincYTcynTLuURZ

The 125 percent rule is a National Electrical Code requirement that states continuous loads during the installation sequence of EV chargers or backup generators cannot exceed 80 percent of a breaker's rated amperage